The PSA layers incorporation onto the PMMA middle layer was made as fabrication steps, during which some issues were encountered as mentioned above.
Yet another redesign will be made to incorporate one circuit in only one half of the disc.
Complete device as per the design established on Friday, Week 12 (Oct 21 - Oct 25)
Water in the source chamber (bottom right) a few seconds after removing from motor
Water in the source chamber (bottom right) three minutes after rotation
The code was updated for the new design.
The rest of the day was dedicated to other academic activities.
There was the intention to make some tests changing the membrane size to see the speed of the reciprocation.
During fabrication, there were some issues, but at the first try, there was no problem.
After the meeting, key activities to do were defined.
Finalize the device
Finalize code for new design